Feature | Task | Priority | Orig. Est. | Current Est. | Elapsed | Remain |
Spell check | Dialog | 1 | 8 (hrs) | 12 | 8 | 4 |
This way, when I go through the book with missing building section, missing HVAC, missing/extra doors called out on the door schedule, missing foundation plan or whatever, at least I'll know roughly, but convincingly, what size is the heap of trouble that I have to deal with. By creating a spreadsheet like this, I can defer or avoid altogether spinning wheels on something not needed to push thing out the door.